Jaw crusher installation steps
Technical articles

Jaw crusher installation steps

Origin:hsmmac    Date:2012-07-07 01:41    Size:Small Medium Big

The jaw crusher is the earliest broken equipment, is also most commonly used a broken equipment, broken in the engineering of jaw crusher is dominant, the other device is auxiliary the equipment of mechanical work, so the jaw crusher installation problem is very important, and other machinery installed, and then to choose the location.

1). The jaw crusher needs to be installed in the shelter, not placing in the open air.

2). The motor to be installed in the jaw crusher's rear, direction of rotation must be done according to the requirements, shall not reverse.

3). The machine should be firmly fixed in the concrete ground, ground to set aside the discharging groove, the inclination of not less than 50 degrees.Basic time users according to the machine and transport equipment and.

4). In adjustment to send material before the mouth, loosen the tension spring, to be adjusted, in the appropriate adjustment of spring tension, spring tension to remove brackets and elbow pads between the noise and the board at work does not easily fall off as appropriate.

5). The jaw crusher and other equipment coordination and management, be conducive to the production, in favor of pipeline operations, ensure working face without congestion.

6). For raw materials and finished products of the convenient transportation, import material is preferably used mechanized transport equipment.

7). The test before tightening the screws and connecting parts, check the lubrication condition.

8). To use human moving pulley, recognized as exercise unhindered, can be run in test, in two hours with no shock, noise, the seal leakage and a belt wheel swing and the shaft loosening phenomenon.Bearing temperature rise no more than 35 degrees, if the above failures must be immediately stopped for inspection.

9). The user load test takes ten hours, and using hard ore such as no more fault and bearing temperature not exceeding 70 degrees, can be put into production.